Project background
| Wanlip STW is Severn Trent’s third-largest sewage treatment facility and is currently undergoing a major upgrade under the AMP8 capital investment programme. The works, led by MWHT, include increased treatment capacity, process improvements, and associated civil works.
A key component of the project is the installation of approximately 350 m above-ground pipeline, extending from existing lagoons to digestion facilities. This pipeline is supported by a combination of low-level bases and elevated gantries, requiring 33 individual pipe support bases (PSBs). RSK’s role involved geotechnical assessment of shallow foundations options at each PSB location, including evaluation of allowable bearing pressures, long-term settlements, and slope stability where applicable. The assessment relied on third-party ground investigation data, including window samples and borehole logs, interpreted to develop a representative ground model.
Despite these challenges, RSK was able to assess the feasibility of shallow spread foundations at each location, minimizing the need for more complex solutions. Where shallow foundations were unsuitable, appropriate recommendations for deep foundations or ground improvement were provided. |